David KrauseDEEN Knowledge Base · Part III · Chapter 7
Part III — Capacity & hour rate Chapter 07 / 18 Reference company Präzisionsteile Muster GmbH Edition v23.2 · 10/2026

Machine hour rate: step by step

Five steps from the asset value to the finished €/h rate — with every intermediate result and control point. This is the calculation that Chapter 6 laid the ground for, worked through completely on one real machine.

€46.37
per machine hour · result
5
calculation steps
3,393 h
productive hours (OEE 78 %)
Example machine 5-axis machining center · built 2018 Acquisition cost €520,000 Shift model Two-shift, Tue–Sat Cost center 210 · CNC milling

7.1 The example: 5-axis machining center in two-shift operation

The following complete calculation shows the machine hour rate for a 5-axis machining center. We work in five steps from the asset value to the finished €/h rate — with all intermediate results and control points.

STEP 1 / 5

Determine the replacement value

Imputed depreciation is based on the replacement value, not the acquisition cost. We use the producer price index of the German Federal Statistical Office (GP09-284 — metalworking machinery).

Replacement-value derivation · cost center 210
ItemFormula / sourceValue
Acquisition costinvoice / purchase contract 2018€520,000
PPI year built 2018Destatis GP09-284, annual average116.4
PPI current 2026Destatis GP09-284, latest annual average149.8
Replacement value = acq. × (PPI₂₀₂₆ / PPI₂₀₁₈)520,000 × (149.8 / 116.4)€669,000
Difference to acquisition cost669,000 − 520,000+€149,000 (+28.7 %)
Control

The replacement value is 28.7 % above the acquisition cost — matching the real price increase for high-performance machining centers between 2018 and 2026. Anyone still using €520,000 as the depreciation base underestimates depreciation by 28.7 % — on this machine, about €10,700/year is then missing from the hour rate.

Bridge to investment planning: the replacement-value rate is silent reinvestment provision

Because imputed depreciation is calculated on the replacement value (€669,000) rather than the historical acquisition cost (€520,000), every productive machine hour earns a share of the future replacement. Over the 13-year technical useful life, €51,462/year flows into the quoted prices — cumulatively the full replacement value. Whoever enforces these rates has mathematically earned the replacement investment by the end; whoever depreciates on acquisition cost silently under-recovers every hour and faces a funding gap at reinvestment.

STEP 2 / 5

Set the technical useful life

Tax useful life per depreciation table: 14 years. Technical-economic useful life for a 5-axis machining center in two-shift operation with good maintenance: 12–14 years. We use 13 years — documented in the asset register.

ItemReasonValue
Tax useful life (depreciation table)BMF depreciation table 2023, item 2.1.114 years
Technical useful life (two-shift)experience value, manufacturer, maintenance log13 years
Imputed depr. = replacement value / useful life€669,000 / 13 years€51,462/year
Book depreciation (comparison)520,000 / 14 years€37,143/year
Difference costing vs. books51,462 − 37,143+€14,319/year
STEP 3 / 5

Calculate imputed interest

Average method imputed interest = replacement value × rate × 0.5
= €669,000 × 5.5 % × 0.5
= €18,398/year  →  €5.42/h at 3,393 h
STEP 4 / 5

Take the productive hours — the time thread

The machine's gross occupancy time becomes the actually chargeable time via the OEE cascade. Only these hours may carry the money mountain from steps 1–3 — anyone calculating with 100 % capacity does not recover their idle costs.

STEP 5 / 5

Sum the components — the knot

Now both threads meet: annual cost (money) divided by productive hours (time) gives the machine hour rate.

MHR components · cost center 210 · basis 3,393 h
Component€/year€/h
Imputed depreciation step 2 · replacement value / 13 y51,46215.17
Imputed interest step 318,3985.42
Energy rated power × load × electricity price30,4358.97
Maintenance service contract + history22,0006.48
Consumable tools purchasing data cost center 21018,5005.45
Space cost m² × rent × 1216,5304.87
MHR = Σ components / productive hours157,325€46.37/MH
Capacity

7.2 Capacity and utilization: OEE, TEEP and the utilization rate

Because the denominator moves the hour rate more than any other figure, it is worth cleanly separating three metrics that are regularly confused in practice.

The same machine, three shift models
MetricSingle shiftTwo-shift ★Three-shift
Gross hours planned occupancy1,904 h4,350 h6,525 h
Productive hours1,485 h3,393 h5,088 h
Utilization (OEE)78.0 %78.0 %78.0 %
Capacity utilization of 8,760 h21.7 %49.7 %74.5 %
TEEP utilization × OEE17.0 %38.7 %58.1 %
resulting MHR€94.42/MH€46.37/MH€33.90/MH
Why both metrics are needed

OEE is identical in all three columns — operations run equally well. TEEP differs by more than a factor of three, and that is exactly what hits the hour rate: from €94.42/MH to €33.90/MH. The shift model is therefore the strongest lever on the MHR — stronger than any OEE improvement. The consequence for costing: a competitor running three shifts can, at identical manufacturing quality, quote a good third cheaper. Whoever loses against such prices does not have a manufacturing cost problem but a utilization problem.

The downtime can be valued directly: 957 hours (4,350 − 3,393) times €46.37/MH is around €44,400 per year — for a single machine. One percentage point of OEE equals 43.5 hours or about €2,000. More depth in the specialist article on production KPIs (DE).

Sensitivity

7.3 Sensitivity analysis: what if parameters change?

The table varies one single variable against the base case each time and shows which parameters must be set particularly carefully.

Scenarioprod. hoursdepr./hMHRΔ
★ Base (two-shift)3,39315.17€46.37—
Single shift1,48534.65€94.42+48.05
Three-shift5,09010.11€33.90−12.47
Replacement value +20 %3,39318.20€50.49+4.12
Capacity 100 % wrong!4,35011.83€36.17−10.20
Useful life 10 y (shorter)3,39319.72€50.92+4.55
Energy +30 %3,39315.17€49.06+2.69
Key insight from the sensitivity analysis

The greatest leverage lies in the shift model: single instead of two-shift almost doubles the MHR (+€48/MH = +103 %). The second critical parameter is the wrong capacity assumption: with 100 % instead of real OEE (78 %) an under-recovery of €8.22/MH arises — multiplied by 3,393 hours = €27,890 of hidden loss per year.

Full hour rate

7.4 Checklist: calculating the MHR

The complete sequence from data gathering to documentation in the BAB — each step with a reference to a chapter or source.

7.5 From the MHR to the full hour rate

The MHR covers only the machine. For a complete manufacturing hour rate, direct labor and the center's residual overhead surcharge are added (direct-labor volume cost center 210: €260,000/year, residual overhead rate 35.1 % from the BAB, Ch. 5.5):

Full hour rate cost center 210   €46.37/MH  machine (MHR)
+ €32.00/h   direct labor
+ €11.23/h   residual overhead 35.1 % on labor
= €89.60/h

7.6 The hour rate in a market downturn

When demand falls, full costing works against the company three times over. Customers order smaller batches, the machine runs fewer hours, and at some point a shift is cut. Each of these steps drives the calculated unit cost up although the part stays the same. The calculation uses the split into fixed and variable cost from 13.1: €97,390 of the MHR is fixed, €17.66/MH varies with run time.

Machine hour rate as a function of run time MHR(h) = fixed machine cost / h + variable rate
MHR(h) = €97,390 / h + €17.66/MH

Effect 1 · The time window shrinks, the hour rate rises

Depreciation, interest, space and the time-based part of maintenance arise whether the machine runs or not. Fewer hours have to carry the same amount.

Cost center 210 · machine hour rate by run time
Scenarioprod. hoursfixed €/MHvariable €/MHMHRΔ
Base, two shifts3,39328.7017.66€46.37—
Two shifts, 70% call-off2,37541.0017.66€58.67+26.5%
Single shift1,48565.5817.66€83.25+79.5%
0 20 40 60 80 100 120 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 productive hours per year€/MH base: 46.37 70% call-off: 58.67 single shift: 83.25 7.3: 94.42 MHR = €97,390 / h + €17.66 energy only variable (7.3) variable share €17.66
Fig. 7.1 · Machine hour rate, cost center 210, over productive hours
Reconciliation with 7.3

The sensitivity analysis in 7.3 shows €94.42/MH for single-shift operation. It lets only energy fall with run time and treats tooling and maintenance as fixed. With the split from 13.1, consumable tooling and half of maintenance also vary, so the rate here rises only to €83.25. Both figures describe the same case under different assumptions; 7.3 is the cautious upper bound.

Effect 2 · Smaller batches make setup more expensive twice over

Setup cost per unit = setup time × MHR / batch size. In a downturn the numerator rises because the MHR rises, and the denominator falls because customers call off smaller quantities. Both movements multiply.

Setup cost per unit · 60 minutes setup time
Batch sizeMHR €46.37 (base)MHR €58.67 (70%)MHR €83.25 (single shift)
50 pcs€0.93€1.17€1.66
20 pcs€2.32€2.93€4.16
10 pcs€4.64€5.87€8.32

From the normal case (batch 50, two shifts) to the crisis case (batch 10, single shift), setup cost per unit rises ninefold. Batch size alone explains a factor of 5; the hour rate explains the rest.

Effect 3 · The surcharge base shrinks

When a shift is cut, direct labor falls as well, by about half of the €260,000. Supervisors, process planning and quality assurance remain. The €91,218 of residual overhead is spread over half the labor cost, and the surcharge rate doubles. The same applies to administration and sales on the basis of manufacturing cost.

Full hour rate, cost center 210 (structure from 7.5)
ItemTwo shiftsSingle shift
Machine (MHR)€46.37€83.25
Direct labor€32.00€32.00
Residual overhead rate35.1%70.2%
Residual overhead on labor€11.23€22.45
Full hour rate€89.60/h€137.70/h

The full hour rate rises by 54%. Anyone who re-quotes on that basis ends up in the vicious circle from 13.5: higher price, fewer orders, even less run time.

The cause is volume, not the shift cut

Cutting the shift does not cause the increase. If the company keeps two shifts at a 70% call-off, actual run time falls just the same and the actual rate rises to €58.67. Cutting the shift is the right response, because it saves real personnel cost. Full costing shows it only as a cost increase because it spreads the remaining fixed costs over fewer hours.

Used capacity cost and idle cost Costing uses the rate at normal utilization: €46.37/MH on 3,393 h.
Idle cost = fixed rate × (h_normal − h_actual)
70% call-off: €28.70 × 1,018 h = €29,217
Single shift: €28.70 × 1,908 h = €54,766

Idle cost does not belong in the quoted price but in the BAB as a volume variance (Chapter 5) and in the monthly report. There it shows what unused capacity costs and prompts the right question.

Permanently lower volume is a capacity question

Normal utilization means the utilization the company expects in the long run. If call-offs stay low over several planning periods, single-shift operation is the new normal and €83.25 is the true full cost. Then no price helps, only adjusting capacity: combining, selling or re-assigning machines (replacement investment, 13.8). Volume risk can be allocated in advance by contract, see 13.9.

What comes in Chapter 8?

Chapter 8 closes Part III with self-diagnosis: the 10 most common costing errors from Chapter 3 are systematically corrected with the methods from Chapters 5–7 — with before/after calculations. Then Part IV begins with the complete quotation costing.

David Krause
Industrial engineer (Dipl.-Wirtschaftsingenieur FH) · 15+ years of cost accounting, plant controlling and maintenance in CNC and die-casting manufacturing. Writes down here what has proven itself in practice.
Profile and CV · Knowledge Base · Contact