David KrauseDEEN Knowledge Base · Part V · Chapter 13
Part V — Steering & decisions Chapter 13 / 18 Reading path calculation chain · steering Edition v23.2 · 10/2026

Contribution margin accounting

Full costing tells you what a part costs. It cannot tell you whether an order below total cost is worthwhile, whether to make or buy, or which order gets the scarce spindle hour. That is what splitting cost into variable and fixed is for.

€60.86
contribution margin I · per unit
6,951
break-even units / year
€17.66
variable MHR · of €46.37

13.1 Separating variable and fixed costs

Variable costs arise with every unit: material, direct labor, energy, consumable tooling. Fixed costs occur whether production runs or not: depreciation, interest, space costs, salaries. The machine hour rate contains both — which is why it has to be split for contribution margin accounting.

MHR components by cost character · CC 210
Component€/yearCharacterReasoning
Imputed depreciation51,462fixedtime depreciation, runs independent of use
Imputed interest18,398fixedcapital commitment
Energy30,435variablearises only during machining
Maintenance22,00050 / 50maintenance intervals partly time-, partly runtime-dependent
Consumable tooling18,500variablewear per cut
Space costs16,530fixedfloor area independent of utilization
Σ variable59,935= €17.66/MH
Σ fixed97,390= €28.70/MH
Σ MHR157,325= €46.37/MH

13.2 CM I, CM II and result

The reference quantity is cost center 210 at full operation: 3,393 productive machine hours, loaded with orders of the titanium-housing type (0.34 h occupancy per unit). That gives about 9,980 units per year — a model calculation that exhausts the capacity exactly.

CM I per unit · titanium housing
Item€/unit% revenue
Net revenue (cash price)182.77100.0 %
− MEK Ti6Al4V85.0046.5 %
− MGK (9.0 %, material-related)7.654.2 %
− DL production9.605.3 %
− DL CAM1.150.6 %
− MHR variable (€17.66/MH × 0.34 h)6.013.3 %
− SEKF special mill4.202.3 %
− SEKF fixture4.802.6 %
− SEKV free delivery3.501.9 %
= Σ variable costs121.9166.7 %
= Contribution margin I60.8633.3 %
Cross-check against full costing

Fixed cost per unit: RGK 3.77 + MHR fixed 9.76 + VwGK 15.57 + VtGK 7.92 = €37.02. Variable costs 121.91 + fixed costs 37.02 = €158.93 — exactly the total cost from Chapter 11. And 182.77 − 158.93 = €23.84 profit. Both calculations describe the same part.

From CM I to result · cost center 210 · year
Item€/year% revenue
Net revenue (9,980 units × €182.77)1,824,045100.0 %
− Variable costs (9,980 × €121.91)1,216,66266.7 %
= Total CM I607,38333.3 %
− Fixed costs of the cost center itself (fixed MHR 97,390 + RGK 91,218)188,60810.3 %
= CM II418,77523.0 %
− Allocated administration and sales (9,980 × €23.49)234,43012.9 %
= Result184,34510.1 %
What this calculation reveals about the order type

Full costing reports €23.84 profit per unit, i.e. €237,923 at 9,980 units. The stepwise calculation arrives at €184,345. The difference of about €53,600 is an under-absorption: through its rates, costing charges only about 72 % of the fixed costs that actually occur in the cost center (RGK €91,218 plus fixed MHR share €97,390 = €188,608).

The reason lies in the part's structure. The RGK surcharge of 35.1 % is calibrated to an annual volume of €260,000 direct labor. But the titanium housing ties up only €10.75 of labor per unit — at 9,980 units that is €107,285, i.e. 41 % of the calculated labor volume. The machine side, by contrast, is covered at 100 %: the 3,393 machine hours are fully loaded.

From this follows a practical rule: parts with high material and machine share but low labor share under-absorb their cost center's residual overhead. Whoever fills their plant exclusively with such orders covers their machines but not their staff organization. Full costing would not have shown this — it would only have reported that every unit brings €23.84 profit.

What your ERP calls “contribution margin”

Many ERP systems show a “contribution margin” or “margin %” on the sales document. By default it is usually calculated as revenue minus unit cost or standard price — that is, against full cost of production, not against variable costs. A warning “margin negative” there means: below cost of production, not: below the price floor. Check which cost value sits behind it in your system before you use it to decide on additional orders.

13.3 Make-or-buy: the classic fallacy

Many companies compare the buy price with the full costs of in-house production. That is wrong: on buying, only the variable costs fall away. The fixed costs remain — as long as the capacity is not actually reduced.

CNC turned part · same case, two calculation paths
ItemMakeBuyDifference
Wrong: full-cost comparison
MEK + variable costs€48.50——
Fixed costs (depr., interest, OH)€61.50——
Full cost in-house€110.00€95.00−€15.00
→ Conclusion "buy is cheaper" — and it is wrong
Right: partial-cost comparison
Variable costs in-house€48.50——
Buy price (decision-relevant)—€95.00+€46.50
→ Make is €46.50 per unit cheaper — the fixed costs occur on buy anyway
When buy is right after all

The calculation flips as soon as the capacity is actually reduced — machine sold, staff reassigned — or when the freed capacity can be filled with better-paid orders. Then the comparison figure is not the fixed-cost block but the forgone contribution margin of the alternative. Add to that the non-calculable criteria: know-how loss, supplier dependency, quality risk, responsiveness to changes.

13.4 Additional order below full cost: when yes, when no?

A customer offers €140/unit for the titanium housing from Chapter 11 — the calculated total cost is €158.93/unit. Decline? The answer depends first on capacity — and then on four conditions.

Item (CC 210)without orderwith order (€140, lot 500)Δ
Utilization70 % (2,375 h)75 % (2,545 h)+170 h
Revenue / year€1,276,648€1,346,648+€70,000
Variable costs (€121.91/unit)€851,541€912,496+€60,955
CM I€425,107€434,152+€9,045
Fixed costs: cost center + allocation (unchanged)€423,038€423,038€0
Result CC 210€2,069€11,114+€9,045
Result: at 70 % utilization, accept

At €140/unit each part covers its variable costs of €121.91 and yields €18.09 of contribution margin. Since the fixed costs occur anyway, every unit above the variable-cost threshold improves the result — even though the price is below full cost. Conversely at full utilization: then the additional order displaces regular orders with a higher CM — here the relative contribution margin per bottleneck hour applies (13.6), and the order should be declined.

-80 -40 0 +40 +80 6,000 6,500 7,000 7,500 8,000 units/year result €k actual 70% +€11,114 (+9,045) +€22,714 +€2,069 €140 for every unit: −€296,679 (fig. 13.3) regular price €182.77 for any extra volume special order €140 · valued at vc 121.91 valued at €98.71 (one-off)
Fig. 13.1 · Result CC 210 around the actual point · additional order 500 units at €140
A kink, not a new line

The additional order only changes the slope from the actual point onwards: €18.09 CM per unit instead of €60.86. The base volume stays at the regular price. A revenue line at €140 starting from the origin describes a different case — price erosion for the entire volume (fig. 13.3). Valued at the additional spending of €98.71, the same order brings +€20,645 instead of +€9,045.

Four conditions before you accept

1. Capacity is really free in the delivery period — not on annual average, but in the weeks in which production takes place.
2. No step-fixed costs arise — no overtime, no extra shift, no temporary staff.
3. No other order is displaced — otherwise 13.6 applies.
4. The price does not spill over — a discount for a regular customer is the new price at the next annual negotiation. Additional orders below full cost belong to cases that can be ring-fenced: a different part, a different market, a one-off quantity.

Whoever accepts purely on “contribution margin positive” fills the shop and still does not cover the fixed costs (13.5).

How low may the price go in the short term?

The €121.91 treats direct labor (€10.75), material overhead (€7.65) and the fixture (€4.80) as variable. For costing that is correct. In the individual case it is too strict: at 70 % utilization the workforce is there anyway, so is purchasing, and the fixture already exists. Additional cash then goes out only for material €85.00, variable machine costs €6.01, special cutters €4.20 and freight €3.50 — together €98.71. That is the absolute floor for the one-off case. €121.91 applies as soon as hours are bought in or fixtures are newly built for the order.

13.5 Break-even

Break-even of cost center 210 BE = fixed costs / CM I per unit

Step 1 — the cost center carries itself:
= €188,608 / €60.86 = 3,100 units/year = 1,054 machine hours = 31 % of capacity

Step 2 — it also carries its share of administration and sales:
= (€188,608 + €234,430) / €60.86 = 6,951 units/year
equals 6,951 × 0.34 h = 2,363 machine hours
of 3,393 available hours = 70 % of capacity

Only from the 6,952nd unit does the cost center earn a profit. Below 31 % utilization it does not even carry its own fixed costs, below 70 % not its share of the company — regardless of how well each individual order is calculated. The 70 % utilization from 13.4 sits exactly at this threshold: that is why the result there is only €2,069.

0 500 1,000 1,500 2,000 0 2,000 4,000 6,000 8,000 10,000 units/year €k/year Capacity 9,980 BE 1: 3,100 · 31 % BE 2: 6,951 · 70 % loss zone profit zone +€184,345 Fixed costs CC Fixed costs incl. allocation Total costs level 1 Total costs Revenue €182.77
Fig. 13.2 · Break-even CC 210 · two fixed-cost levels · capacity 9,980 units = 3,393 h

Price erosion: when the exception price becomes the regular price

Price for the entire volume · fixed costs €423,038 · vc €121.91
PriceCM I per unitBreak-evenUtilizationResult at 9,980 units
€182.77 (regular price)€60.866,951 units70 %+€184,345
€164.30 (minimum price)€42.399,980 units100 %±€0
€160.00€38.0911,106 units111 %−€42,900
€140.00€18.0923,385 units234 %−€242,500
0 1,000 2,000 3,000 4,000 0 5,000 10,000 15,000 20,000 25,000 units/year €k/year beyond capacity Capacity 9,980 BE 6,951 · 70 % BE 11,106 · 111 % BE 23,385 · 234 % Total costs revenue €182.77 revenue €160.00 revenue €140.00
Fig. 13.3 · Revenue fan under price erosion · break-even moves beyond the capacity limit
The positive-CM trap

Every price above €121.91 yields a positive contribution margin. Whether it covers the fixed costs is decided by capacity: below €164.30 the break-even lies beyond 9,980 units — the shop is full, the result negative. The variable floor applies to the single order, this one to the entire volume.

Unit costs: the full-cost death spiral

Full cost per unit = €121.91 + €423,038 / volume
Utilizationunits/yearfixed cost per unitfull costvs. price €182.77
50 %4,990€84.78€206.69−€23.92
70 %6,985€60.56€182.47+€0.30
85 %8,483€49.87€171.78+€10.99
100 %9,980€42.39€164.30+€18.47
100 140 180 220 260 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 units/year €/unit 50 %: 206.69 70 %: 182.47 100 %: 164.30 ch. 11: 158.93 less volume → higher price → less volume full cost vc + F/x price 182.77 vc 121.91 98.71 (one-off)
Fig. 13.4 · Full cost per unit over volume · CC 210
Fixed cost per unit is a consequence of utilization, not its cause

Whoever recalculates at full cost as volume falls raises the quoted price — and loses more volume. At 50 % utilization the titanium housing "costs" €206.69, at full utilization €164.30. The part is the same. Reconciliation with Chapter 11: the costing shows €158.93, the curve ends at €164.30. The difference of €5.37 per unit is the under-absorption of residual overheads from 13.2 (€53,600 / 9,980 units).

Step-fixed costs: extra volume beyond capacity

Third shift · model assumption Step-fixed costs of 3rd shift (shift supervision, standby): €60,000/year
Three-shift capacity (ch. 7.2): 5,088 h / 0.34 h = 14,965 units

Extra volume at which the shift pays for itself: €60,000 / €60.86 = 986 units → from 10,966 units
Additional order of 500 units with extra shift: €121.91 + €60,000 / 500 = €241.91/unit
-100 0 100 200 300 400 500 6,000 7,500 9,000 10,500 12,000 13,500 15,000 units/year result €k 2 shifts 9,980 3 shifts 14,965 €184,345 −€60,000 step step recovered at 10,966 units without step (fictitious) result with 3rd shift (+€60,000 fixed)
Fig. 13.5 · Result CC 210 with step-fixed costs of a third shift

The €60,000 is a model assumption, not a figure from the reference company. The logic holds for any amount: an additional shift only pays if the extra volume covers the step at least once — at €60.86 CM per unit, with 986 units. For a single order beyond capacity, the entire step is spread over its volume.

13.6 Contribution margin per bottleneck hour

CM I per unit answers the question "is this order worthwhile?". Once the machine is fully loaded, the question changes fundamentally: no longer "is A worthwhile?", but "A or B — which order gets the scarce spindle hour?". Here the per-unit contribution margin misleads.

Two orders competing for the same machine
OrderCM I per unitbottleneck time per unitCM per bottleneck hour
A€1800.90 h€200.00/h
B€2601.60 h€162.50/h
The ranking reverses

Order B, with €260, has the higher per-unit contribution margin and looks more attractive on the quotation sheet. Related to the scarce spindle hour, it clearly loses: A brings €200/h, B only €162.50/h. For every 100 bottleneck hours that run on A instead of B, €3,750 more contribution margin arises. Whoever prioritizes by per-unit CM when the machine is full gives money away.

0 150 300 450 600 0 500 1,000 1,500 2,000 2,500 3,000 bottleneck hours/year cum. CM €k €607,613 €588,600 Δ €19,013/year A: €200/h B: €162.50/h rank by CM per bottleneck hour: A first rank by CM per unit: B first
Fig. 13.6 · Cumulative CM over 3,393 bottleneck hours · demand A 1,500 h, B 2,400 h (model assumption)
Loading the bottleneck machine by two rankings
Rankinghours Ahours BCM I / year
CM per bottleneck hour (A first)1,500 h1,893 h€607,613
CM per unit (B first)993 h2,400 h€588,600
Difference: 507 h × €37.50/h€19,013
Consequence for the price floor

When the machine is fully loaded, the short-term price floor rises above the variable costs: every accepted order displaces another. The displaced contribution margin per bottleneck hour must be added as opportunity cost. For the titanium housing the CM per machine hour is €60.86 / 0.34 h = €179.00/h — this value is also the right valuation figure for unplanned downtime, as used by the article on maintenance strategy.

13.7 Three price floors — one function of utilization

Short term, bottleneck, long term: these are not three rules but three sections of the same curve. Which one applies is decided by utilization in the delivery period.

100 140 180 220 260 30 % 40 % 50 % 60 % 70 % 80 % 90 % 100 % 110 % 120 % 130 % utilization CC 210 €/unit extra shift for 500 units: 241.91 displacement: 121.91 + 60.86 = 182.77 idle: 121.91 98.71 206.69 182.47 164.30 bottleneck spare capacity long run: full cost vc + F/x short run: vc · bottleneck: vc + c/h × t one-off 98.71
Fig. 13.7 · Price floor of the titanium housing over utilization of CC 210
Decision matrix · CC 210 · titanium housing
SituationRecognisable byCurvePrice floorRuleSect.
Idle, one-offstaff and fixture in place, nothing bought inresult kink, fig. 13.1€98.71price > additional spending13.4
Idle, standard casefree hours in the delivery periodresult kink, fig. 13.1€121.91CM > 0 and four conditions13.4
Price for the entire volumeprice round, framework contract, market pricerevenue fan, fig. 13.3€164.30break-even within capacity13.5
Permanent priceseries part, annual negotiationunit costs, fig. 13.4€158.93 / €164.30cover full cost at planned activity11, 13.5
Extra volume beyond capacityextra shift, temporary staff neededresult step, fig. 13.5€241.91 (500 units)extra volume ≥ step / CM = 986 units13.5
Bottleneckmachine full, orders competeCM per bottleneck hour, fig. 13.6€182.77rank by CM per bottleneck hour13.6
At full utilization the cheaper alternative applies

An additional order on a full machine can displace another order (€182.77) or trigger an extra shift (€241.91 for 500 units). The price floor is the cheaper of the two options — here displacement. If it displaces orders with a lower CM per bottleneck hour, the floor falls accordingly.

All curves with your own figures: Calculator: cost curves and price floors.

13.8 Every cost has an expiry date

Rule of thumb Variable costs expire with the order, fixed costs with the contract.
Every costing system freezes a time horizon. The question is not which system is right — but whether its horizon fits your decision.

Fixed and variable are not properties of a cost type but a question of commitment period. Production labor is committed until the next shift plan, administrative and sales staff until the end of the notice period, the hall until the lease ends, the machine until the replacement decision. For a decision, exactly those costs count whose commitment ends or begins within the decision horizon. The longer the horizon, the more costs become controllable — and the higher the price floor.

Titanium housing · costs by end of commitment (figures from 13.2 and 13.4)
Decision horizoncommitment additionally ends for+ €/unitprice floor
single order, weeksmaterial, variable machine costs, special cutter, freight98.71€98.71
quarterproduction labor and CAM, material overhead, fixture23.20€121.91
1–3 yearsresidual overhead, administration, sales — staff and contracts27.26€149.17
asset life, ≈ 13 yearsimputed depreciation, interest, space, time-dependent maintenance9.76€158.93
80 110 140 170 200 weeks quarter 1–3 years ≈ 13 years decision horizon €/unit 98.71 material, cutter, freight 121.91 + labor, mat. OH, fixture 149.17 + resid. OH, admin, sales 158.93 + depr., interest, space regular price 182.77 price floor = costs whose commitment ends within the horizon
Fig. 13.8 · Price floor of the titanium housing by decision horizon
In the long run every calculation ends at full cost

The last step is exactly the full cost from Chapter 11. Whoever calculates with partial costs in the long run adds all fixed costs back step by step and arrives at the same figure. In the long run partial costing delivers nothing different — it only makes the path visible. Two subtleties remain: what counts is the future payment, not the past one; that is why depreciation is based on replacement value (6.4). And full costing is right in total, but per product only as good as the allocation — hence the €164.30 from 13.5.

Which horizon each system silently freezes
Systemfrozen horizontreated as fixedblind spot
Full costinglong — plant and staff permanentlynothing, everything allocated per unitwrong for the single decision
Contribution marginone period, usually the plan yeareverything not reducible within the yearhard cut: what could be terminated in three months still counts as fixed
Flexible and marginal standard costingthe plan yearthe same cut, built into planningcapacity steps only appear in the next plan
Activity-based costingmedium to long termlittle — overheads controllable via activitiesassumes back-office capacity is actually reduced
Target costinglife cycle incl. developmentnothingno tool for short-term decisions
Relative direct costing (Riebel)none — several, staggeredordered by commitment period and notice periodmakes commitment explicit; laborious, rare in practice
Two traps

Sunk costs: if the material is already in stock, the price paid is irrelevant to the decision. What counts is the replacement cost or what the material would earn elsewhere.
Cost stickiness: fixed costs build up faster than they come down. A shift is set up quickly but only reduced through notice periods and contracts. Additional orders that tie up capacity permanently are therefore more dangerous than one-off ones.

13.9 Volume risk: who carries the fixed costs when call-offs fall?

A framework agreement covers 9,980 titanium housings a year at €182.77. The customer reduces inventory and calls off only 6,985 units, or 70% of the planned volume. For the customer this is working capital management. For the contract manufacturer the cost center's result falls from €184,345 to €2,069. Cost accounting makes the damage visible; only the contract can prevent it.

Two degression effects, but only one depends on call-offs

Batch-size degressionUtilization degression
Costsfixed per order: setup, CAM, first articlefixed per period: machine, building, staff, administration
Driverquantity per batchquantity per year
In this book10.4 and 17.3: setup share below 1–2% from batch 5013.5: full cost €164.30 at full and €182.47 at 70% utilization
Levercut setup time (SMED), combine batchesallocate volume risk by contract, fill capacity elsewhere
When call-offs fallthe customer pays via the batch-size price scalewithout a clause, the contract manufacturer pays

Shorter setup times make small batches cheaper. They do nothing against a falling annual call-off, because the €423,038 of fixed costs stay the same whether the part comes in four batches or forty. In a market downturn both effects come together, and if a shift is cut, the machine hour rate and the surcharge rates rise as well. The calculation is in 7.6.

The damage in figures

Titanium housing · cost center 210 · plan vs. 70% call-off
Plan70% call-offDifference
Volume9,9806,985−2,995
Revenue (€182.77)1,824,0451,276,648−547,396
Variable cost (€121.91)1,216,662851,541−365,120
Contribution margin607,383425,107−182,276
Fixed cost incl. allocation423,038423,0380
Result184,3452,069−182,276

The difference equals the lost contribution margin exactly: 2,995 units × €60.86. Fixed costs have not risen; they are just spread over fewer units.

Five contract models at a 70% call-off

ModelClauseCompensationResultof plan
A · Pure unit price€182.77/pc, no compensation02,0691%
B · Volume corridor ±15%fixed-cost share per unit below 8,483 pcs63,49865,56736%
C · Fixed-cost recharge€42.39 per missing unit at the cut-off date126,954129,02370%
D · Two-part price€35,253/month + €140.38/pcin base fee129,02370%
E · Take-or-pay on CM€60.86 per missing unit182,276184,345100%
Formulas · P = planned volume, x = call-off, f = F / P B: compensation = max(0; P × (1 − corridor) − x) × f
C: compensation = max(0; P − x) × f
D: base fee = F / 12 · unit price = v + planned profit / P
E: compensation = max(0; P − x) × (p − v)
Covering fixed costs is not covering profit

Below plan, C and D are economically identical. Both cover the fixed costs in full and earn €18.47 per unit delivered. The gap to E is €55,322, which is the profit on the volume not called off. Anyone who negotiates only fixed-cost cover gives that up. That can be right, but it should be a deliberate decision.

The difference between C and D lies in cash flow and enforcement. The base fee arrives monthly and is undisputed. The recharge arrives only at the cut-off date, as a claim against a customer who is trying to save money. In return, D costs upside: at 120%, the contract manufacturer earns €221,214 under D and €305,821 under the pure unit price.

Re-pricing at full cost leads into the vicious circle from 13.5

A clause such as “recharge based on full cost of the actual volume” raises the unit price to €182.47 full cost plus markup. The markup then also applies to fixed costs that were never incurred additionally. The customer refuses, and the new price becomes the baseline for next year. The correct approach compensates only the under-recovery: missing volume times fixed-cost share per unit of the planned volume.

Consignment stock: working capital only changes balance sheets

A consignment stock solves the customer's problem, not the supplier's. The contract manufacturer produces in economic batches, the customer withdraws as needed and pays only on withdrawal. The inventory disappears from the customer's balance sheet and reappears on the supplier's.

Consignment, titanium housing · call-off 6,985 pcs/yr
ItemBasisValue
Monthly call-off6,985 / 12582 pcs
Batch size3 months of demand1,746 pcs
Safety stock½ month of demand291 pcs
Average inventorybatch / 2 + safety stock1,164 pcs
Capital tied up× manufacturing cost €131.94 (ch. 11)€153,600
Imputed interest× 5.7% (yield curve)€8,755/yr · €1.25/pc
Residual stock at phase-outup to batch + safety stock2,037 pcs · €268,800
Consignment only with three clauses

The residual stock risk of €268,800 is 130 times the actual result of €2,069. Three points therefore belong in the contract: interest compensation or a storage fee from the day of storage, here €1.25 per unit; a maximum stock level, for example two months of demand; and an obligation to take over residual stock at phase-out or a call-off stop, valued at manufacturing cost. The free storage period from the article on toll machining follows the same logic.

Calculator · Call-off riskPre-filled with cost center 210 and the titanium housing · values editable
70 %

Result over call-off · shaded area = corridor

A · Unit priceB · CorridorC · RechargeD · Two-partE · Take-or-pay
ModelClauseCompensationResultof plan

Consignment stock held by the contract manufacturer

13.10 Checklist

What comes in Chapter 14?

Chapter 14 picks up the OEE from Chapter 7.2 again — this time as a management task: how do you measure downtime reliably, how do you prioritize improvements, and what does one percentage point actually bring?

David Krause
Industrial engineer (Dipl.-Wirtschaftsingenieur FH) · 15+ years of cost accounting, plant controlling and maintenance in CNC and die-casting manufacturing. Writes down here what has proven itself in practice.
Profile and CV · Knowledge Base · Contact