David Krause Knowledge Base · Part IV · Chapter 12
Part IV — Quotation costing Chapter 12 / 18 Continuation case study A · titanium housing Edition v23.1 · 07/2026

Post-calculation: the plan-actual comparison

A pre-calculation is a forecast. Whether its assumptions held, you only know once the order is done — and only if you recalculate. Here the planned profit of €23.84 shrinks to €9.58 per unit, and the numbers say exactly why.

€9.58
actual profit · plan €23.84
+€14.26
cost overrun per unit
−59.8 %
profit vs. plan

12.1 Why post-calculation is indispensable

A pre-calculation is a forecast. It rests on standard times, experience values and assumptions about material and tool life. Whether those assumptions were correct, you only know once the order is done — and only if you recalculate.

Companies that skip post-calculation cost for years with standard times no one ever checked. The typical course: the pre-calculation is set up carefully once, then copied for similar parts — and the creeping deviation only shows up when the year-end result no longer adds up.

The actual function

Post-calculation serves calibration, not blame. Its result is not "the order went badly" but "our standard times here are 19 % too optimistic". Whoever uses it as a control instrument against production gets whitewashed feedback and loses exactly the data basis they wanted to improve.

12.2 Data sources

QuantitySourceTypical pitfalls
Actual timesshop-floor feedback (BDE), machine datasetup time booked to one order although several orders benefit from it
Actual materialstock withdrawals, goods receiptoffcut and scrap parts not booked along
Actual toolingtool issue per cost centerorder allocation missing — then only recordable as overhead
Surcharge ratesBAB (Chapter 5)for post-calculation the same rates are used as in the pre-calculation
Same rates on both sides

In post-calculation the plan surcharge rates are deliberately used, not the year's actual rates. Otherwise two effects are mixed: the single order's variance and the cost center's over- or under-absorption. Both are interesting — but separately. The cost-center variance belongs in the absorption control from Chapter 5.6.

12.3 The plan-actual comparison

The order from Chapter 11: titanium housing Ti6Al4V, lot 50, calculated net cash price €182.77 per unit. After completion the shop-floor feedback is in.

Plan-actual comparison per unit · lot 50
ItemPlanActualVar.%Cause
Direct material85.0089.40+4.40+5.2 %Ti surcharge per purchase document
Material overhead (9.0 %)7.658.05+0.40+5.2 %follows MEK
→ Material costs92.6597.45+4.80+5.2 %
Direct labor production9.6011.47+1.87+19.5 %actual time 21.5 vs. 18.0 min
Direct labor CAM1.150.88−0.27−23.5 %CAM time 55 vs. 60 min
Residual overhead (35.1 %)3.774.33+0.56+14.9 %follows DL
Machine costs (MHR × time)15.7718.32+2.55+16.2 %occupancy 23.7 vs. 20.4 min
SEKF special mill4.206.80+2.60+61.9 %tool life halved
SEKF fixture4.804.800.000.0 %as planned
→ Manufacturing costs39.2946.60+7.31+18.6 %
→ Cost of production131.94144.05+12.11+9.2 %
VwGK + VtGK (17.8 %)23.4925.64+2.15+9.2 %follows HK
SEKV free delivery3.503.500.000.0 %terms unchanged
→ Total cost158.93173.19+14.26+9.0 %
→ Profit per unit23.849.58−14.26−59.8 %price was fixed
The result

The order cost €14.26/unit more than calculated — at lot 50 that is €713.00 of extra cost. The planned profit of €1,192.00 shrank to €479.00. Three drivers, by weight: the SEKF mills wore out twice as fast as planned (+€2.60), the machine occupancy ran 16 % over plan (+€2.55), the machining time at the operator 19 % above it (+€1.87).

Notable is the counter-movement: the CAM programming was five minutes faster than planned. It compensates barely a seventh of the time overrun — too little to turn the result, but a pointer to where the pre-calculation was too cautious.

12.4 Classifying variances systematically

Not every variance requires the same action. The following systematics orders them by cause and urgency:

TypeTypical causesActionPriority
Time variance DL, MHRImprecise standard-time studies · new machine or operator · underestimated setup complexityAdjust standard times, document experience values from post-calculationhigh
Tool over-consumption SEKFHarder material than expected · wrong cutting data set · quality fluctuationRaise SEKF assumption, optimize cutting data, tool monitoringhigh
Scrap and reworkTolerance exceeded · tool wear · programming errorBuild scrap rate into the calculation, improve production releasehigh
System error calculation-based causeWrong MHR · outdated BAB · superseded capacity assumptionUpdate BAB and MHR — affects all orders, not just this onehigh
Material price varianceRaw material price · currency effect · small-quantity surchargeKeep MEK current, framework contracts, risk surcharge on volatile materialsmedium
Positive varianceBetter cutting data · learning curve · setup optimizationDocument and adopt as new standard valuesmedium
The most dangerous category

System errors look like order variances but aren't. If the machine hour rate is wrong or the BAB outdated, every order deviates — only no one notices, because the cause is sought at the single order. The test: if several independent orders show the same variance direction, the problem lies in the costing basis, not in production.

12.5 The learning-curve effect

For repeat orders, post-calculation regularly shows a learning-curve effect: each repetition runs faster, because operator and machine are set up for the part. The widespread 80-percent learning curve holds that at every doubling of cumulative quantity the manufacturing time falls to 80 % of the initial value.

Titanium housing over five orders · each lot 50
Ordercum. unitssetup actualunit time actualDL var.Effect
1st5078 min21.5 min+18.6 %first order — baseline
2nd10065 min19.8 min+8.6 %−8 % from learning curve
3rd20060 min18.5 min+3.3 %approaching the standard unit time
4th50058 min17.8 min−1.1 %below standard — adjust calculation
5th1,00056 min17.2 min−3.9 %set new standard time: 17.2 min
What this means for costing

From the third follow-on order the actual times should be adopted as new standard times. Whoever keeps costing with the original values becomes systematically too expensive and loses follow-on orders — in the example, at the fifth order the calculation would sit 3.9 % above the actual time. Conversely: whoever applies the run-in times to a first order under-costs. The clean approach is separation — apply a justified start-up surcharge for first orders and show it in the quotation, then the customer also understands why the second order comes cheaper. Rule of thumb: update standard times after the third order, then review annually.

12.6 Checklist

What comes in Chapter 13?

Chapter 13 leaves the full-cost view. It splits costs into variable and fixed components and thereby answers questions full costing cannot: is an order below total cost worthwhile? Make or buy? From what quantity does the cost center carry itself?

David Krause
Industrial engineer (Dipl.-Wirtschaftsingenieur FH) · 15+ years of cost accounting, plant controlling and maintenance in CNC and die-casting manufacturing. Writes down here what has proven itself in practice.
Profile and CV · Knowledge Base · Contact