9.1 The four methods
| Method | Principle | Suited to | Limit |
|---|---|---|---|
| Division costing | total cost / quantity | one product, mass production | fails with variants |
| Equivalence figures | convert variants via ratio numbers | batch production with proportional differences | the ratio must be stable |
| Surcharge costing | overhead as a percentage on direct costs | single-part and small-series production | distorts with unequal cost centers |
| Machine hour rate | machine costs per hour, remainder as surcharge | capital-intensive production with differing assets | higher recording effort |
9.2 When does introducing the MHR pay off?
Machine-hour-rate costing is more involved than a blanket surcharge. It pays off as soon as the cost centers differ markedly — and that is precisely the rule in machining.
| Cost center | MHR | Surcharge | Full hour rate |
|---|---|---|---|
| 200 · CNC turning | €20.13/MH | 39.8 % RGK | €64.87/h |
| 210 · CNC 5-axis milling | €46.37/MH | 35.1 % RGK | €89.60/h |
| 240 · assembly | — | 60.8 % FGK | €51.46/h |
The table shows both in the same company: the machine cost centers run via the MHR, assembly deliberately stays on the differentiated FGK surcharge (60.8 %). That is not a contradiction but the correct allocation — each center is charged via the quantity that drives its costs.
9.3 Differentiated FGK surcharge or MHR?
Not every company needs machine hour rates. A company with differentiated FGK surcharges — its own percentage per cost center — is far ahead of the blanket surcharge and can be entirely sufficient for labor-intensive production. The decision hangs on a single figure: the machine cost share per center.
| Cost center situation | Right method | Why |
|---|---|---|
| Labor-intensive, low machine tie-up (assembly, welding, inspection) | differentiated FGK surcharge | overhead follows personnel deployment — the labor reference is correct |
| Mixed, machine cost share < 30 % | differentiated FGK surcharge suffices | distortion from the labor reference stays within tolerance |
| Machine cost share > 30 %, homogeneous park | MHR per center group | one rate for similar machines is enough, effort manageable |
| Machine cost share > 30 %, heterogeneous park | MHR per machine/cost center | only the individual MHR captures the large rate differences (see 9.5) |
A differentiated FGK rate becomes dangerous when applied to a capital-intensive center whose machine costs do not correlate with labor. Example: an automated turning center runs unmanned — little direct labor, high machine costs. An FGK surcharge "on labor" charges far too little overhead there, because the reference base (labor) is small while the actual costs (machine) are large. Exactly this case demands the MHR — the differentiated surcharge cannot catch it.
9.4 Decision matrix: which method?
Answer the criteria and choose the method with the most hits for your situation. ★ = especially suited.
| Criterion | Blanket | Area-based | CC-based | MHR ★ |
|---|---|---|---|---|
| < 10 employees | ✓ | ✓ | ||
| 10–30 employees | ✓ | ✓ | ✓ | |
| > 30 employees | ✓ | ✓ | ||
| Homogeneous machine park | ✓ | ✓ | ✓ | |
| Heterogeneous park (CNC, die casting, assembly) | ✓ | |||
| Machine costs > 30 % of manufacturing costs | ✓ | ✓ | ||
| Single-part / small-series production | ✓ | ✓ | ✓ | ✓ |
9.5 Four machine types in MHR comparison
The same methodology from Chapter 7 (replacement-value basis, technical service life, OEE productive hours, six cost components), applied to four real asset types — directly comparable.
| Machine | RV | SL | hprod | Σ €/year | MHR €/MH |
|---|---|---|---|---|---|
| Injection molder 250 t (3-shift) | €215k | 12 yr | 4,609 | €70,202 | 15.24 |
| CNC 5-axis machining center (2-shift) | €410k | 10 yr | 2,819 | €96,040 | 34.07 |
| Die casting (Al, 2-shift) | €520k | 9 yr | 3,100 | €148,000 | 47.74 |
| Laser cutting system (2-shift) | €580k | 8 yr | 3,254 | €181,900 | 55.90 |
The factor of 3.7 between the cheapest and dearest machine shows why a blanket rate necessarily cross-subsidizes in a mixed park.
If the full hour rates of the manufacturing centers differ by more than about 20 percent, a blanket surcharge is no longer defensible. In the reference company, 74 percent lie between assembly and 5-axis milling — here a blanket rate would be grossly negligent. For three similar turning machines, by contrast, a common rate suffices.
9.6 Activity-based costing: when it pays off
The four methods above allocate the costs of production. The indirect areas — purchasing, work preparation, design, order processing — still run through percentage surcharges. That is acceptable as long as these areas are small and all orders use them in a similar way. Where that no longer holds, the surcharge distorts: it allocates by value, but the work arises per transaction.
| Purchase order | Material value | Surcharge 9 % | Activity cost rate |
|---|---|---|---|
| 100 titanium blanks, one line | €8,500 | €765.00 | €30.00 |
| 20 standard parts, one line | €40 | €3.60 | €30.00 |
Both orders cause the same effort: request, order, book goods receipt, check the invoice. The surcharge loads the expensive material with 25 times that effort and the cheap one with an eighth of it. Expensive material subsidizes small orders — visible in the quotation price, invisible in its cause.
It pays off as soon as the indirect areas make up a large share of costs and orders use them very differently: variant production, special-purpose machinery and plant engineering, companies with many small orders. There the design or order-processing hour is the real cost driver, not the machine hour.
It does not pay off as a company-wide system in a contract manufacturer with few indirect staff. A side calculation for one or two activities — cost per order line, per quotation, per set-up — alongside surcharge and machine hour rate costing is enough.
Target costing starts at the other end — with the price set by the market or the customer. When it works for manufacturing companies and where the job shop reaches its limit is shown in 9.7.
9.7 Target costing: from the target price back to costs
All methods so far calculate forwards: costs plus markup give the price. Target costing calculates backwards. The market or the customer names the price; after deducting the target margin, the allowable costs remain. The difference to your own costs (drifting costs) is the target cost gap — it has to be closed in design, material or process before the part goes into production.
Allowable costs at 15 % profit on full cost (as in ch. 11): 160.00 / 1.15 = €139.13
Own full cost (ch. 11): €158.93
Target cost gap: 158.93 − 139.13 = €19.80 per unit = 12.5 %
| Cost block | €/unit | share | Lever | Job shop |
|---|---|---|---|---|
| Material Ti6Al4V incl. material overhead | 92.65 | 58 % | near-net-shape blank, material, source | only with customer approval |
| Machine (MHR variable + fixed) | 15.77 | 10 % | occupancy time: −0.06 h = −€2.78 | yes — own process |
| Labor, CAM, residual overhead | 14.52 | 9 % | multi-machine operation (16.3) | yes |
| Special direct costs | 12.50 | 8 % | depreciate fixture over a framework quantity | yes, with volume commitment |
| Administration, sales | 23.49 | 15 % | none in the short run | no |
| Full cost | 158.93 | 100 % |
On its own, a job shop only reaches machine, labor and special direct costs — together €42.79 per unit, realistically a fraction of that. If a gap remains, contribution margin accounting decides: €160 is above the variable costs of €121.91, the contribution margin is €38.09. As an additional order with free capacity the price is acceptable (13.4). As the price for the entire volume it is not: break-even would be 11,106 units, 111 % of capacity (13.5).
| Company type | Target costing | Form |
|---|---|---|
| Series manufacturer with own development | yes, fully | target cost splitting onto functions and assemblies before the design is fixed |
| Supplier with design responsibility | yes | customer target price as a given, design-to-cost, agreed annual price reductions built in |
| Job shop working to customer drawings | limited | backward calculation against the target price, levers in the own process, design only via change proposals |
| One-off and special production without a market price | no | quotation costing (ch. 10) |
Actual target cost splitting — distributing allowable costs over functions and components by customer value — requires design authority and belongs in product development. For the job shop the backward calculation above is enough: in five minutes it shows whether a target price is reachable and which cost block would have to move.