David Krause Knowledge Base · Part IV · Chapter 11
Part IV — Quotation costing Chapter 11 / 18 Reading path calculation chain · station 6 Edition v23.1 · 07/2026

Three case studies

The scheme applied to three real processes: CNC titanium milling, plastic injection molding and aluminum die casting. Each brings its own peculiarity — tool wear, mold cost allocation, sprue and recirculated material — and each ends at a price floor.

53 %
material share · titanium part
10×
mold allocation A vs. B
+20 %
gross material · die casting
How to read the three case studies

Case study A uses the rates of the reference company this book uses throughout — it is the direct continuation of Chapter 7. Case studies B and C come from other companies with their own BAB, because injection molding and die casting do not occur in the reference company. Their surcharge rates are therefore deliberately different; each case study carries its own profile.

Case study A

11.1 CNC 5-axis milling: titanium housing, lot 50

Machine5-axis machining center
Cost center210 · CNC milling
MHR€46.37/MH
MaterialTi6Al4V
SurchargesMGK 9 % · RGK 35.1 % · VwGK 11.8 % · VtGK 6 %
Profit15 %
Costing per unit · lot 50
ItemRate€/unitNote
Direct material Ti6Al4V85.00ERP purchase price
+ Material overhead9.0 % MEK7.65CC 100
→ Material costs92.65
Direct labor production€32/h × 0.30 h9.60net machining time
Direct labor CAM€48/h × 0.024 h1.15programming time per unit
+ Residual overhead35.1 % DL3.77CC 210
+ Machine costs€46.37/MH × 0.34 h15.77MHR from Ch. 7
+ SEKF special mill4.20HSC titanium mill, wear
+ SEKF fixture€240 / 504.80order-specific
→ Manufacturing costs39.29
→ Cost of production131.94
+ Administrative overhead11.8 % HK15.57CC 300
+ Selling overhead6.0 % HK7.92CC 400
+ SEKV free delivery3.50per terms
→ Total cost158.93
+ Profit margin15 % SK23.84segment target
→ Net cash price182.77lot 50 = €9,138.50
Where the margin on this part is decided

At €85.00 of €158.93 total cost, the titanium blank alone makes up 53 %. The entire manufacturing block comes to €39.29 — less than half the material. For such parts, purchasing decides the result more than production. A five percent material price rise costs more margin than a ten percent time saving at the machine brings in. The post-calculation in Chapter 12 shows exactly that.

Case study B

11.2 Plastic injection molding: ABS housing cover

Machineinjection molder 250 t
Cost center220 · injection molding
MHR€15.26/MH
Shift modelthree-shift
SurchargesMGK 3 % · VwGK 8 % · VtGK 4 %
Profit12 %

The methodological peculiarity of injection molding is the mold. It is product-specific and therefore does not belong in the machine hour rate, but is allocated across the quantity as a special direct cost. How it is allocated is a commercial decision with substantial price impact:

Mold cost allocation · mold €35,000
VariantLogicper unitWhen it makes sense
A — total lifetime€35,000 / 500,000 units€0.07series product with framework contract and secured off-take
B — per call-off€35,000 / 50,000 units first order€0.70first order with uncertain follow-on quantity — hedges the investment
C — customer propertymold billed separately€0.00customer commissions the mold themselves
The factor of ten between A and B

Variant A and B differ by a factor of ten — for a part whose entire total cost is in the range of a few cents, that is the difference between profit and loss. Whoever costs with variant A and then receives a call-off of only 50,000 units has €31,500 of mold cost uncovered. So always regulate two things contractually: the off-take quantity the costing assumed, and who owns the mold.

Case study C

11.3 Aluminum die casting: gearbox housing

Machinecold chamber 630 t
Cost center230 · die casting
MHR€52.80/MH
MaterialAlSi9Cu3
SurchargesMGK 4 % · VwGK 7 % · VtGK 5 %
Profit14 %

Die casting brings a peculiarity no machining calculation knows: a considerable part of the material input never becomes the part. Sprue and overflows go back into the melting furnace — they are neither fully cost nor fully free.

Material calculation per unit
ItemValueExplanation
Net part weight1,850 ggearbox housing AlSi9Cu3
+ Sprue and overflows370 g20 % of net weight
= Gross material requirement2.22 kgthis is the purchase quantity
− Scrap credit recirculated material−€0.220.37 kg × €0.60/kg
The most expensive costing error in die casting

Whoever takes the net weight as material requirement understates the input by 20 %. The sprue must be purchased, melted, conveyed and remelted — only the material value partly returns, the energy for it never. Conversely it is just as wrong to ignore the scrap credit: then the part is computationally €0.22 too expensive and you lose orders you could have won. Both figures belong shown — and the reference base for the sprue is always the net weight.

Price floors

11.4 Minimum price and short-term price floor

Not every price must cover full costs — but every cost accountant must know where the limits lie. For the titanium housing from case study A:

Floor€/unitMeaning
Target price182.77normal case — covers full costs and profit
Long-term price floor158.93total cost — no profit, but all costs covered
Short-term price floor121.91variable costs — contribution margin zero
Absolute minimum95.75only MEK and DL — every order below destroys substance
When the short-term floor applies — and when it doesn't

A price between €121.91 and €158.93 improves the result only if the capacity would otherwise stand idle and no better-paid orders are displaced. If the station is fully loaded, every such order costs the forgone contribution margin of the displaced one. And there is a third danger no calculation captures: prices once accepted become the reference for the next order. The framework for this is in Chapter 13.

What comes in Chapter 12?

Chapter 12 takes case study A and compares the pre-calculation with the actual shop-floor feedback: where was the planning off, and what did it cost? The result up front — profit shrinks from €23.84 to €9.58 per unit.

David Krause
Industrial engineer (Dipl.-Wirtschaftsingenieur FH) · 15+ years of cost accounting, plant controlling and maintenance in CNC and die-casting manufacturing. Writes down here what has proven itself in practice.
Profile and CV · Knowledge Base · Contact